LOCATION
Sindri unit is located about 20 kms away from the district headquarters of Dhanbad district of Jharkand state. This is the first fertilizer unit in India. Later on it was modernised in the year 1974.

COMMENCEMENT
Mainly this is a LSHS / Fuel Oil based Urea manufacturing plant. Sindri Modernization Project was conceived in the early seventies for modernizing the Sindri Unit which had become uneconomical due to old age, poor qualities of available raw materials and technical obsolescence of the process. The techno-economic feasibility report for addition of new ammonia and urea production and ancillary facility was prepared and submitted to the FCI Board and the Government in May 1971. The Government gave clearance to the project in November, 1973. Simultaneously the World Bank was approached by the Government of India for financing the Project. The World Bank accorded its approval in principle to finance the project in October 1974. The project was taken up for implementation with Zero date as the 29th October 1974 with a time schedule of 48 months.
as
The project consists of single stream 900 tpd Ammonia Plant and a single stream 1000 tpd urea Plant and auxilliary facilities such as Steam generation plant, Bagging Plant, BFW treatment Plant, Coal, Ash and Oil Handling facilities. The erection and commissioning of the project got delayed mainly due to delay in supplying compressors and SGP Boilers by M/s BHEL. Commercial production of the plants started from October 1979 against the original schedule.


TECHNOLOGY FOR EACH PLANT /PRODUCT

Name of the Plant : Ammonia
Name and source of supply of raw materials required Petroleum Product(heavy fraction)from IOC Refineries.
Name of utilities required : Water, Steam and Electricity
Name of the process :

Gasification of feed stock (shell partial oxidation)
Desulphurisation (Lurgi Rectisol Process)
Shift conversion (Lurgi H.T.Conversion)
Decarbonation (Lurgi Rectisol Process)
Final purification (Linde Liquid Nitrogen wash)
Air Separation Unit (Linde)
Ammonia Synthesis (Halder Topse & Uhde)
Refrigeration Unit (M/s Borsig, Germany)

   
Name of the Plant : Urea
Name and source of supplyof raw materials required Ammonia and CO2 from own Ammonia Plant
Name of Utilities required : Water, Steam and Electricity
Name of Process route and plant designer : Total recycle process (Modified Technimont Process).
   

MAIN PRODUCTS /BY PRODUCTS /INDUSTRIAL PRODUCTS
S.No. Plant/Product Annual Installed Capacity (MT)
  A Ammonia 297000
  B Urea 330000
  C Ammonium Nitrate 18000
  D Ammonium Bi-Carbonate 4500
  E Nitric Acid (53%) 78870

PERFORMANCE    

The maximum overall capacity utilisation achieved by the unit is 75.5 % upto 31.3.2000.

 

Plant stopped production on 16-3-2002.